Brief Description of 1. Works

Project name: annual output510,000 tons of functional sugar (alcohol) project

Project Nature: New

Construction unit: Shandong Xingguang Capital Biotechnology Co., Ltd.

Construction site:Economic and Technological Development Zone, Leling City, Dezhou City, Shandong Province (North of Jinjin East Road)

Total investment:30486Ten thousand yuan

Project content: The production workshop and its supporting facilities are planned to be built. The main raw materials of the products are: glucose, maltose syrup, etc. Production process: fermentation, biological enzyme reaction, decolorization, desalination, concentration, drying, etc. After completion, it can be processed to produce galacto-oligosaccharides10000tons/year, isomaltooligosaccharide 10000tons/year, edible erythritol 30000tons/year

Land nature and land area: total land area60340m2(90.51mu).

2. the pollution of the project and its possible impact on the environment

1. Exhaust gas: organized particulate matterDischarge concentration meetsIntegrated Emission Standard for Regional Air Pollutants (DB37/2376-2019)requirements,VOCSThe emission concentration and emission rate meet the requirements of VOC Emission Standard No.7Part:OtherIndustry (DB37/2801.7-2019) Medium Table1Requirements. The unorganized emission source of the project is"RunEmit, drip and leak "exhaust gas can be discharged up to the standard at the factory boundary.

2Wastewater: the wastewater discharged from the Project can meet the requirements of wastewaterInlet water quality requirements for treatment station. The project wastewater is not directly discharged into the surface water body, which has little impact on the surrounding environment.

3. Solid waste The solid waste of the proposed project shall be reasonably disposed or treated after classified collection and reasonable temporary storage, and shall not be discharged to the environment, which conforms to the disposal principles of "harmless", "reduction" and "resource utilization" of solid waste, and will not affect the external environment.

4. Noise: After the project takes shock absorption, noise elimination and sound insulation measures for each noise source, the noise at the boundary of the factory meets the "Emission Standard for Environmental Noise at the Boundary of Industrial Enterprises" (GB12348-2008) Medium 2requirements of the class standard.

5. Environmental risk: this project does not involve major risk sources, and risk prevention measures such as accident pools are built in the project area, which will not have a great impact on the surrounding environment.

Key Points of 3. Environmental Impact Assessment Conclusions Proposed in the Environmental Impact Report

1. This project is in line with the national industrial policy;

2. The project has taken limited prevention and control measures for the pollutants generated in its production process, which can meet the discharge standards;

3. The pollution control process adopted in this project is reasonable, the total amount of pollutants produced has been greatly reduced, and the emission is small;

4. After the completion of the project, the current situation of regional environmental quality will not be changed.

4. the manner and duration of public access to environmental impact reports

The public can check the simplified version of the evaluation report at Shandong Xingguang Capital Biotechnology Co., Ltd. within ten working days from the date of this announcement. For further additional information, contact the construction unit or evaluation unit by telephone or email.

Scope and Main Matters of the 5. for Public Comments

The main purpose of this announcement is to understand the public's perception of the main environmental factors that affect the lives of residents, such as ambient air quality, surface water, groundwater, noise and environmental risks in the evaluation area, and the impact of the project on the local economic development after the project is completed and put into operation. Attitudes towards the impact of residents' lives and whether they agree with the construction site of the project.

Name and contact information of 6. construction unit

Construction unit: Shandong Xingguang Capital Biotechnology Co., Ltd.

Address: Economic and Technological Development Zone, Leling City, Dezhou City, Shandong Province (North of Jinjin East Road)

Contact: Minister Zhou            Telephone:15315888354

Mailbox:850124943@qq.com

7.Name and contact information of EIA unit

Environmental Impact Assessment Unit: Shandong Environmental Protection Science Research and Design Institute Co., Ltd.

Address: Lishan Road, Lixia District, Jinan City, Shandong Province50No.

Contact: Guo Gong            Telephone:13791088976

Mailbox:285514599@qq.com

8.Starting and ending time for public comments

PublicCanFrom the date of publicity of this project10a jobWithin days, put forward valuable opinions to the construction unit.

See Annex for the Form of Public Comments1.

                                    Shandong Xingguang Capital Biotechnology Co., Ltd.

2021Year12Month23Day